Week 14 - Saturday 28th August Work has progressed
on stripping the paint from the stone columns and arches of the
Church. It is nearly complete and has been hard and
dirty work, but the results are amazing.
The old lighting system has been removed. link
Week 13 - Saturday 21st August Work
continues
removing
paint
from the columns and restoring them
to
natural stone link
Week 12 - Saturday 14th August Again
work
continues
removing
paint
from the columns and restoring them
to
natural stone. link
Week
11
-
Saturday
7th
August Work
continues
removing
paint
from the columns and restoring them
to
natural stone. link
Week 10 - Saturday 31st July Work
began
this
weekremoving
paint
from the columns and restoring them
to
natural stone. link
Week 9 - Saturday 24th July BIG
DECISION
This
week
the
big
decision
of
the
project was made.
In consultation with the architects it was decided we would have a
water
based under floor heating system, the heat source being gas boilers
housed in
what was the confessional near the sacristy.
Very serious consideration had been given to a ground source for the
heat using bore holes. This would be
environmentally friendly, renewable, but financially beyond our reach
to
install, especially as the Government has cancelled the Low Carbon
Buildings
Programme – Phase 2 funding for heat pump installation. A new
concrete slab will be laid in the
church, which will be insulated. If at a
future date ground source heat became preferable, it could be linked to
the new
system. This week the heating pipes and
radiators have been removed. On Monday
work will begin on removing paint from the columns and restoring them
to
natural stone. link
Week 8 - Saturday 17th July The
asbestos
removal
people
have
now
completed
their
work.
The stone
flooring in the sanctuary is being
removed in preparation for the underfloor heating.
link
Week 7 - Saturday 10th
July
The
asbestos
removal
people
have
finished
in
the
boiler
house
and
underground
passageways
and
have
moved
into the church. Most of
the sanctuary floor has been taken up. Click
on
photo
or
link
Week 6 - Saturday 3rd July This
week
the
High
Altar
has
been
carefully
dismantled.
Likewise
the
Baptismal
Font
which
will
be
refurbished
and
replaced in front of the Lady Chapel.The asbestos removal people are working in
the cellar of the house where the heating boilers are and the
passageways for
the pipes underground. Click
on
photo
or
link
Week 5 - Saturday 27th June This
week
the
front
altar
has
been
dismantled
and
preparatory
work
done
on
the
High
Altar.
The
parish
of
Our Lady of Mount Carmel in Redditch
is interested in the front part of the
High
Altar.The
stonemasons removed the square of stone
over the relics to reveal a silver box, a little larger than a
matchbox, with a
red ribbon on it and sealed with wax.These relics will be placed in the new altar when it is
consecrated. Click
on
photo
or
link
Week 4 - Saturday 20th June Click
on
photo or link
Week 3 - Saturday 13th June Work
has
continued
during
the
week
protecting
the
Statues,
Stations
and
woodwork.A number of exploratory holes have been made
in the floor as it is not of a uniform construction or level. Click
on
photo
or
link
Week 2 - Saturday 6th June
Work has
continued
during the week protecting the Statues, Stations
and woodwork. A number of exploratory
holes have been made in the floor as it is not of a uniform
construction or
level. One of the pictures shows the site manager Derek Monahan, Site Manager
with Father Garry.
Click on photo or link
Friday 5th June
Within the Parish of St Osburgs is the Coventry
Canal.
James Brindley, known as the "father" of the British canal
system, was commissioned to build the canal in 1768. Located on high ground on the edge of the city
centre the Y-shaped canal basin has fine examples of surviving canal
architecture with more than 200 years behind it. The 5½
mile stretch of canal
between Coventry Basin and Hawkesbury Junction has been transformed
from a forgotten backland into the city's longest park. Combining the
natural peace and beauty of the countryside with Coventry's rich
industrial heritage, the canal provides the perfect setting for an
unusual walk - whatever your interest. Within the canal basin is a
Statue of
James Brindley, known as the "father" of the British canal
system. Fr Garry often has a walk around this area to better
understand the heritage of Coventry. http://en.wikipedia.org/wiki/Coventry_Canal.
The photograph shows
the bronze statue of James Brindley and Father Garry, both looking at
their plan of work. James Brindley looking out onto the canal and
Father Garry over his Parish. Click on photo or link
Week 1 Saturday
30th
May
2010
-
Preparing
the
Way
"Midland Conservation Ltd,
moved on to the site at 6.30am Monday morning with the delivery of
their
office, toilets, and storage container; and security fencing. A
plumber and electrician connected supplies
for them. During the week the carpenters
have been protecting the features of the church. On Tuesday the
organ builders came and
removed a number of the big pipes into the loft of the Parish Hall and
sheeted
the organ to protect it during the work.
Sound engineers removed the sound system from the Church and
reinstalled
it in the parish hall. Unfortunately it
was not possible to transfer the “Loop System”, but a new one will be
installed
in the Church. On Tuesday also,
volunteers moved a number of the church benches into the parish
hall. On Wednesday the temporary altar furnishings
were put in place. On Thursday the first
Mass was said and further work was done on the benches, and all the
choir
resources were carried over to the hall.
On Friday the Statues of the Sacred Heart, and Our Blessed Lady, were
taken down, washed and put in place in the parish hall. On Saturday,
after the
morning Mass, the first Baptism took place.
All in all an eventful and happy week!
We
are indebted to those who made possible the move from the church to the
parish
hall. We especially thank Derek
Woodward, supported by Veronica, who made the temporary altar, the
tabernacle
plinth, altered and covered the stage screen, and put up supporting
shelves for
the statues."
Sunday 23rd May 2010
Before, Click on photo or link
"Today the Feast of Pentecost, Our Last Sunday in the Church in
its present condition. After all our
patient
waiting, work will now start on St Osburg’s this coming week. We
ask the guidance of the Holy Spirit on our
project. During the week we will move
into the parish hall for Mass and the celebration of the Sacraments for
the
duration of the work, which is scheduled for 40 weeks. It will
probably be February 2011 before we
are back in the church. There will be no Mass or Eucharistic
Service on Monday, Tuesday or
Wednesday as we move out of the Church.
Help Needed I need three able bodied helpers at 9am on
Monday morning to move the Hall chairs into the loft. Please see
me. We need two more helpers after Mass on Monday
to help clean the Hall. Please see
me. On Tuesday we hope to move the
required benches into the Hall; the Organ will be partly dismantled and
the
pipes transferred to the loft; the sound system will be transferred to
the
Hall. " Canon Gary Byrne newsletter
Easter Sunday 4th April 2010
" GO-AHEAD FOR THE RESTORTION OF ST OSBURG’S The Diocesan Treasurer has
given approval for us to undertake the Restoration of St Osburg’s.
We have half the money needed for the internal work on the Church and
can proceed with that,
while we borrow the remainder. We are not at the moment however, in a
position to build the
toilets or improve the main entrance to the Church. But it is great
news that we can start on
the main work. There will be discussions with the builders and
architects after Easter and I will
tell you the programme when it is known." Canon Gary Byrne newsletter